# KODE NAMA BUDGET REALISASI ESTIMASI SALDO
1BCM21-0001Catu Daya/Power189,000,00072,900,000116,100,000
2BCM21-0002Access Network Batam Area4,114,070,8001,948,357,5002,165,713,300
3BCM21-0003Access Network Bintan Area3,702,977,500353,385,0003,349,592,500
4BCM21-0004Customer Premises Equipment/CPE1,565,000,00001,565,000,000
5BCM21-0005Air Conditioner125,000,00057,800,00067,200,000
6BCM21-0006ISP Development 1,108,600,000529,493,000579,107,000
7BCM21-0007Measuring Instruments and Tools112,900,000-109,000,000221,900,000
8BCM21-0008TGW - Point of Interconnection/PoI366,000,00028,580,000337,420,000
9BCM21-0010Office Equipment 310,000,000127,062,000182,938,000
10BCM21-0011Office Furniture150,000,00043,803,800106,196,200
11BCM21-0012Building Improvement530,000,000220,970,000309,030,000
12BCM22-0001Batam Backbone & Backhaul 1,480,000,000872,128,000607,872,000
13BCM22-0002Bintan Backbone & Backhaul772,099,0000772,099,000
14BCM22-0003Access Network Nasional Area2,900,000,0001,600,000,0001,300,000,000
15BCM22-0004Batam Network Access Equipment284,000,000161,900,000122,100,000
16BCM22-0005Bintan Network Access Equipment172,000,0001,625,000170,375,000
17BCM22-0007IP Multimedia Subsistem/IMS28,000,000028,000,000
18BCM22-0008Intangible Asset145,901,00096,067,10249,833,898
19BCM22-0009Vehicles1,430,000,0001,430,000,0000
20BCM22-0010Nasional Backbone & Backhaul7,335,468,000-5,457,071,35312,792,539,353